ABSTRACT Without true finite capacity scheduling, any implementation for manufacturing execution, whether it is ERP, SCM, or MES, cannot realize the goal of enterprise efficiency and agility. All aspects of OM for manufacturing execution fall behind the lead of FCS, which is the bridge between planning and execution. Real tangible return on assets rests with FCS. INTRODUCTION Integrating a diverse collection of resources to accomplish a goal is an issue that has faced humankind since the first city arose and food and services needed to be provided to the populace.

The modern challenge for operations management (OM) is the speed and volume that data is presented to OM systems. This explosion of data holds the promise of efficiency and agility unrealized in the past, but it forces the attention of analysts and engineers to convert the flood of data into a useable form to move from planning to action. All the systems such as MES, SCM, and ERP are information hungry beasts that must be fed with the right information at the right time to direct enterprise resources. OM requires a well-coordinated dispatch of its resources to realize efficiency and agility.

This paper addresses the need to look at OM from an information-centric perspective as a necessary complement to emerging process-centric views. This discussion moves to the execution systems, also treated from an information-centric perspective, and concludes with a discussion as to why finite capacity scheduling (FCS) is the key to OM for manufacturing execution. WHEN DATA BECOMES INFORMATION Despite the advances in information technology, notably object-oriented software, systems continue to be defined by functional decomposition.

Functional decomposition creates complex definitions with fragile coupling and cohesion that are on one side of a great chasm from the reality of the methods that are used to build modern information systems. Information itself is an under designed component of modern systems. Information is a series of objects made from atoms of data. Data becomes information only through context and inferences derived from context. A good example is the use of spreadsheets to attempt to understand data rather than the use of application software designed to with the operational context in mind. Figure 1: Hierarchy of Data Fusion Inferences

Figure 1 shows the hierarchy of inferences through a process called data fusion. Data fusion simulates the cognitive processes used by humans to continuously integrate data from their senses to make inferences about the external world. Information systems collect data though sensors and other assets, and in the hierarchy of data processing, multiple data sources are combined to approximate or estimate the condition of some aspect of the enterprise operation. This is the first translation of data to a level of inference. Parametric data is processed to begin specific identification of a situation.

As more parametric data are collected, different aspects of the situation come together to allow a contextual analysis of an increasingly complex set of conditions. Once integrated, the situation can be compared to the goals or desired state of the system. Parallel to the types of data processing are the types of inference. With raw data an inference can be made of the general condition. While this level of inference rarely points to a specific correction action, it does begin to isolate what subsystems require attention. The next level of inference will reveal a specific characteristic behavior of the system.

With more integrated data, the identity of an operational system or process is revealed. The next inference is the behavior of a process, which then leads to an assessment of a situation. At the highest levels of inference, the performance is assessed to determine the deviation from the performance goals, acceptable risks, or desired state. Data fusion is not a new concept, having its origins in simple scouting, but has come into its own since WWII. The use of data fusion systems as an information springboard for systems design places execution aspects of OM firmly into a modern framework of information systems engineering.

WHAT WAS OLD IS NEW AGAIN As mentioned in the introduction, operations management has been, and remains, one of the greatest organizational challenges throughout history. OM arises from the need to coordinate diverse resources to meet the needs of a complex system. The concept of the plan-execute-control model, a “discovery” made by analysts in the late 1990’s, appears in the historical records of systems management, one of the earliest mentions circa 4th century BC in China. One of the more versatile models in modern systems management appeared in 1977 as a result of a joint effort between Dr J.

S. Lawson of the Naval Electronic Systems Command and Dr. Paul Moore of the Naval Postgraduate School. Figure 2 shows the Lawson-Moore model, adapted by the author for general resource management. SENSE is the collection of raw data or other collateral information about the observed environment. PROCESS takes the data through the inference hierarchy, integrating data within the context of the tasks required of the managed resources. The situation as best can be determined with the resources is then compared to the DESIRED STATE.

The DESIRED STATE is the result of planning, which drives the allocation of resources to tasks. The plan exists in generalities, except for enterprises where goals are achieved with simple tasks assigned to few or uncomplicated resources. DECIDE is the point where the comparison of the situation to the goals will dictate what corrective actions are needed to bring the performance of the enterprise in line with the plan. ACT is the direct management of resources to alter enterprise performance to close the gap between the current state and the DESIRED STATE.

The Lawson-Moore model is a closed-loop execution model, continuously integrating data, making inferences about the environment, and managing resources to meet goals of the plan. The Lawson-Moore model does not address planning, but it does unite planning and execution. To develop an execution system, it is important to understand the distinction between planning and execution. Figure 2: Lawson-Moore Model (aka Lawson Model) PLANNING AND EXECUTION Planning and execution are related, but not one and the same.

Planning does not occur during execution; the plan should be formulated to allow for variations and alternate execution strategies. Business (or manufacturing or service) processes are set in place, serving as doctrine that unites actions within the enterprise. Processes should be compiled for all resource management, and serve as a set of procedures designed to achieve the best results from a united enterprise, while allowing for inspired actions and initiatives. The enterprise doctrine exists so that laborious planning for each individual operation need not repeated with every new plan.

The more complex or unstable composition of enterprise resource, the greater the need for standardized procedures. This becomes the foundation of repeatable performance, reducing human variations to the least contributor of performance variations. Planning cannot deviate greatly from doctrine, and execution will fail without doctrine. It is possible that execution will look so different from the plan that the uninitiated will see no similarity, but if the goals of the plan are achieved, then the execution is successful.

The next section will unite the inference model with the Lawson-Moore model to develop an information-centric execution model. DATA FUSION AS OPERATIONS MANAGEMENT SYSTEM Figure 3 shows the execution system that arises from merging inference and the Lawson-Moore model. For main components exist in this system: information collection, execution environment, human-machine interface (HMI), and evaluation. Information collection includes sensors and all other information gathering, and is a critical component to the resources managed by the OM system.

The HMI is the primary means by which operators interact with the OM system. Evaluation is the component that applies performance measurements and other measures of effectiveness to determine the degree to which the execution system is meeting the goals of the plan. The execution system performs the data fusion, situation definition, and resource management. Figure 3: Data Fusion as Execution Environment Data flows from sensors contained in resources through data filtering to begin building inferences. Filtered data enters three levels of information processing.

Level 1 processing aligns data in time, insures consistent units of measure, and accounts for any other physical aspects of the data. Data from different sources are aligned or correlated in order to develop meaningful inferences (e. g the color of the box has little to do with its volume, but its height, length, and width has a direct bearing on computing volume). The final function of Level 1 is identifying the situation for further processing in Levels 2 and 3. Level 2 assesses the situation within the context of the fusion process in use and available information from Level 1.

Level 2 may require algorithms to augment sparse or missing data. Level 3 evaluates the situation and may direct actions to modify the use of resources to minimize deviations from plan goals. The communications between the three processing levels is continuous, forming an information loop within the execution environment to adapt to changes in the external environment. Short term and long term (historical) databases form the decision support system for the OM system. Corrective action can be automatic or require operator intervention as dictated by operation procedures.

THE COMMON DENOMINATOR The integrated systems view for the enterprise is emerging as analysts focus on process-centric models and away from product- and information-centric models. Evidence is the REPAC model from AMR, shown in Figure 4. Recognizing the shortcomings of the functions intense MES and SCOR models, AMR developed a model that is focused on the business processes while supporting component assembly. Comparing that process-centric model with the information-centric model, common elements emerge.

The main theme in REPAC COORDINATE is the need to schedule detailed activities from PLAN, utilizing feedbacks from EXECUTE and ANALYZE. These are the same themes addressed by the Lawson-Moore model. In both models, the key element is the ability to manage resources at the individual operations to achieve the goals set by the plan. This level of resource management is achieved by dynamic capacitated scheduling, supported by the real-time data from the environment and comparisons to the desired state established by the plan. Figure 4: AMR REPAC Model FCS: THE KEY TO OPERATIONS MANAGEMENT

Whether OM is approached from a process- or information-centric model, finite capacity scheduling drives how resources are deployed to perform the tasks required to achieve the goals of the plan. The sequence of operations, the materials and labor required for operations, and the output of the operations all require supporting resources to act in sync with the business of implementing the plan. Finite capacity scheduling with the ability to account for multiple resource constraints and complex scheduling goals will be scalable to schedule both the lowest level of operation and the supporting resources.

Planning is at best an approximation of the resource needs because planning cannot develop a precise quantification of labor, material, or time to meet the goals. Execution cannot begin until the set of actions, well matched to the available resources, is developed to load the operations and develop a timeline for the actions. Execution cannot continue unless the scheduling component can receive the feedback from the resources and develop alternative sets of actions that will best meet the goals of the plan.

Only true finite capacity scheduling, design for real-time use, can integrate the planning and execution together to meet the enterprise objectives. CONCLUSION For manufacturing OM to achieve the goals of efficiency and agility, all aspect of planning, execution, and control are necessary to create an effective system. The bridge from the plan to the actions of the organization is dynamic resource management. For an organization with any degree of complexity, procedures need to be in place to establish the general guidelines of operations. In this imperfect world, the plan and procedures must be flexible enough to adapt.

The control side provides data and accepts corrective action, but a dynamic element must exist in the OM system that allows for accepting a situation assessment and rapid response to degrading performance. The planning side requires feedback from the OM layer to create future plans. The baseline provided by planning drives the selection of enterprise operations, but the synchronization of these operations, and the alternative actions needed when the exceptions arise, comes from the power of true finite capacity scheduling. FCS is the means by which OM for manufacturing execution becomes a reality.

Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with MyStudyWriters
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
English 101
IThank you
Customer 452631, April 6th, 2021
Business Studies
Thank you very much for a good job done and a quick turn around time.
Customer 452615, March 31st, 2021
Human Resources Management (HRM)
excellent job
Customer 452773, July 17th, 2023
Human Resources Management (HRM)
excellent, great job
Customer 452773, June 19th, 2023
Human Resources Management (HRM)
excellent
Customer 452773, July 11th, 2023
FIN571
excellent work
Customer 452773, March 1st, 2024
Leadership Studies
awesome work as always
Customer 452773, August 19th, 2023
Philosophy
Thank you
Customer 452811, February 17th, 2024
History
Looks great and appreciate the help.
Customer 452675, April 26th, 2021
Business and administrative studies
Perfect
Customer 452773, February 23rd, 2023
BUSINESS LAW
excellent job made a 93
Customer 452773, March 22nd, 2023
Business and administrative studies
looks good thank you
Customer 452773, March 3rd, 2023
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat
Close

Sometimes it is hard to do all the work on your own

Let us help you get a good grade on your paper. Get professional help and free up your time for more important courses. Let us handle your;

  • Dissertations and Thesis
  • Essays
  • All Assignments

  • Research papers
  • Terms Papers
  • Online Classes
Live ChatWhatsApp