RC design

Table of contents

This submission presents the method statement and corresponding temporary work design for the construction of low-rise building (LRB). Footing foundation will be chosen for the foundation of structure. Design calculation and drawing for the structure, Including beams, columns, foundations, walls, floor slabs will be shown in the following categories. Furthermore, formwork will be adopted for the construction of structure and timber formwork will be the first priority. . Summary of RC Structure Dimension Element Member Size (mm) Type of formwork Foundation Timber Slab 250 Beam 500 x 500 x 5000 ‘Ofs 150 Column 500 x 500 All concrete works shall conform to the General Specification as following: Elements Grade wall Blinding layer Reinforcement 35 260, 460 MPa 4. Competent Persons for Constructions of the Low-rise Building (LRB) Structure Construction Manager ; Engineer – He shall supervise all technical items of construction works of MPS 2 structure, but not limited to the following items:

  1. To handle the difficulties during the construction.
  2. All required tests arrangement and Submission to the Engineer
  3. Prepare the erticality monitoring records and submit to the Engineer
  4. To prepare, manage and implement the documented system in compliance with statutory requirements.

Construction Supervisor/ General Foremen – He shall be full time on site to supervise the following works.

  1. To supervise and arrange all the MPS 2 construction works.
  2. To arrange and monitor all relevant tests to structural works.
  3. To arrange all setting-out works for MPS 2 structure constructions.
  4. To follow the approved method statement for construction

Safety Officer – He/ She shall be full time on site. His/ Her major duties are carrying ut regular checking on the implementation of the safety measures adopted with reference to regulations. Safety Supervisor – He shall be full time on site. His major duties are assisting the Safety Officer to carry out regular safety checking and supervise the construction works for the safety aspects.

Environmental Officer – He shall be full time on site to oversee all the environmental and sanitary issue during the construction. Surveyor – He shall be full time on site. His major duties are carrying out the site setting-out and monitoring works including verticality checking, settlement of ground measurement until completion. Certified Workers – They must be at least 18 years old and be a holder of a certificate issued by a person whom the Treatment Plants. The contractor shall ensure the certified workers being physically and mentally suitable for construction works. 5.

Plants Plants and equipments Lifting appliances Air Compressors Generator Water pumps Portable pneumatic breaker Welding Machine Hand tools Carpenter Rebar fixer Concretor General Labour According to the site condition and requirement of completion of each phase, the site operation will be arranged in stages corresponding to different site logistic plans at ifferent time frame of construction. The overall sequence of construction is generally divided into following stages:

Stage 1 (Excavation)

  1. Carry out underground utilities detection
  2. Excavate down to +4. 3mPD to 3. 1 mPD
  3. Perform compaction

Stage 2 (Foundation) A. Steel preparation

  1. According to the drawings, prepare the steels with appropriate length, bending angle and diameter.
  2. According to the drawings, placing the steels in corresponding location and spacing.
  3. Pack the steel together, extra steel bend inwards to prevent exposing outside the concrete.
  4. Leaving some space for trimming bar

B. Formwork

5. Ensure the working area is clean and clear, and with appropriate ligament.

6. According to the drawing, install the timber on the surrounding and fix tightly with nails and screw. Make sure there aren’t any gaps.

7. Brush an oil layer on the inner face of timber.

C. Concreting

8. Ensure the strength of concrete is with required slump

9. Placing blinding layer on the bottom of foundation.

10. Placing concrete evenly on the area. For separated injection, each layer should not exceed 450mm tall

11. Perform compaction with vibration tube. Note that ibration tube should not place next to the timber and not to control the flow of concrete.

12. Flatten the top of concrete when appropriate level of concrete is placed.

13. Timber can be removed after 16 hours and check whether there are cracks.

14. Perform curing by cover the concrete with plastic sheet and Floor Slab

  1.  According to the drawings, prepare the steel with appropriate length, diameter, bending angle, shape.
  2. According to the drawings, placing the steels in corresponding location, and spacing.
  3. Pack the steel together, extra steel bend inwards to prevent exposing outside the concrete.
  4. Leaving some space for trimming bar
  5. Placing concrete evenly on the area. For separated injection, each layer should not exceed 450mm tall
  6. Perform compaction with vibration tube. Note that vibration tube should not place next to the timber and not to control the flow of concrete.
  7. Flatten the top of concrete when appropriate level of concrete is placed.
  8. Timber can be removed after 16 hours and check whether there are cracks
  9. Perform curing by cover the concrete with plastic sheet

Construction procedure

  1. Excavation and Compaction
  2. Construct foundation
  3. Reinforcement bar fixing .
  4. Formwork elevation
  5. Concreting and curing
  6. Construction of first floor
  7. Column
  8. Reinforcement bar fixing
  9. Formwork elevation
  10. wall
  11. Reinforcement bar fixing
  12. Formwork elevation
  13. Bearn
  14. Reinforcement bar fixing
  15. Formwork elevation
  16. Floor Slab
  17. Reinforcement bar fixing
  18. Formwork elevation
  19. Concreting
  20. Construction of second and third floor, same as construction of first floor temporarily.

Environmental Protection Measures Any spoil, debris or silt from construction works area shall be deposited at esignated area within the site as specified in the waste management plan. Such spoil, debris and silt shall be immediately removed and avoid falling into adjacent areas. Drip/ spill trays will be provided to all machines and the fuel storage tanks or drums. All power equipment shall have proper silencers. Construction plant will be kept in good condition and will be properly maintained. Construction activities will be limited to daytime hours as far as possible. All construction works will be carried out limited to the approved working hours subject to the approval of Environmental Protection Department (EPD) and Drainage Services department (DSD).

Frequently cleaning and watering the site area to minimize dust emissions. Burning debris or any material shall be prohibited on site at all times. Air and noise pollution will be monitored on a regular basis in accordance with the Air Quality & Noise Management Plan. Noise permit shall be obtained from the Environmental Protection Department (EPD) prior to any construction work beyond normal working hours. Chemical waste discharge license shall be obtained before any chemical waste disposed offsite. Surface runoff water arising from the site shall be collected by temporary drainage system.

Such temporary drainage system composed of sand bags and temporary channels along the site boundary. The collected surface runoff shall be de-silted at the sedimentation tanks before discharged to public drainage system. The temporary drainage management plan has been submitted separately. Wheel washing bays will be located at the entrances in order to keep a good housekeeping condition inside the site.

Contingency Plan

Lifting appliances such as mobile cranes can be deployed on site in order to speed p. Catch up the progress of works. In addition, some major heavily E&M equipment will be handled by the addition cranes on site. Material availability such as concrete, reinforcement and formwork can be delivered on site shortly. Normally, 1 – 2 days’ advance ordering period is required for the processing from ordering to on site delivery. In view of the current market, no shortage of aforesaid material supply is found. Disposal of the material system has already been set-up. All disposal records and submissions are in order in compliance with statutory requirements.

Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with MyStudyWriters
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
Leadership Studies
excellent job
Customer 452773, August 26th, 2023
Human Resources Management (HRM)
excellent, great job
Customer 452773, June 19th, 2023
English 101
great summery in terms of the time given. it lacks a bit of clarity but otherwise perfect.
Customer 452747, June 9th, 2021
Business and administrative studies
Thank you
Customer 452773, March 19th, 2023
BUSINESS LAW
excellent job made a 93
Customer 452773, March 22nd, 2023
FIN571
excellent
Customer 452773, March 15th, 2024
Leadership Studies
excellent job
Customer 452773, August 3rd, 2023
Business and administrative studies
Excellent job
Customer 452773, March 9th, 2023
Social Work and Human Services
Although it took 2 revisions I am satisfied but I did receive it late because of that.
Customer 452603, March 25th, 2021
Business and administrative studies
Thank you for your hard work and effort. Made a 96 out of 125 points Lacked information from the rubic
Customer 452773, October 27th, 2023
ACC/543: Managerial Accounting & Legal Aspects Of Business
EXCELLENT JOB
Customer 452773, January 10th, 2024
Leadership Studies
awesome work as always
Customer 452773, August 19th, 2023
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat
Close

Sometimes it is hard to do all the work on your own

Let us help you get a good grade on your paper. Get professional help and free up your time for more important courses. Let us handle your;

  • Dissertations and Thesis
  • Essays
  • All Assignments

  • Research papers
  • Terms Papers
  • Online Classes
Live ChatWhatsApp